CAG Flags Gaps in Jharkhand PSUs, Points to Delays and Idle Assets
The CAG report highlighted delays in projects, idle assets and pending MSP payments in Jharkhand’s public sector undertakings.
Published
6 months agoon
Jharkhandinc Bureau
RANCHI, March 16: The Comptroller and Auditor General (CAG) of India has flagged structural and operational gaps in Jharkhand’s public sector undertakings (PSUs), pointing to delays in project execution, idle assets, and lapses in financial management, according to its report for the period ending March 2023.
The report was tabled in the Jharkhand Assembly on March 16.
An audit of the Jharkhand State Building Construction Corporation Limited (JSBCCL) showed that out of 1,328 projects worth more than Rs 14,000 crore undertaken since 2015, only about 55 percent have been completed. Several projects remain stalled, dropped, or at initial stages.
According to the report, the corporation did not prepare a corporate budget for several years and lacked a technical committee to assess project feasibility. In multiple cases, projects were taken up without detailed estimates, while issues such as land availability, delayed handover and contractor-related problems affected execution.
The audit also pointed to instances where completed assets remained unused. A degree college building constructed at a cost of about Rs 12 crore could not be utilised due to its proximity to a high-tension transmission line. Similarly, infrastructure created for Jharkhand Raksha Shakti University, involving expenditure of over Rs 12 crore, remains incomplete.
The report said some completed buildings were not handed over to user departments for extended periods, leading to deterioration and additional maintenance costs.
Delays in project completion were also observed across several works, resulting in cost escalations. In select cases, price adjustments led to additional expenditure of more than Rs 42 crore. The CAG noted that shortages of engineering staff affected supervision and monitoring.
In a separate audit of the Jharkhand State Food and Civil Supplies Corporation Limited (JSFCL), the report highlighted gaps in paddy procurement and delays in Minimum Support Price (MSP) payments to farmers.
Between 2018-19 and 2021-22, the state did not meet procurement targets, and payments to farmers were delayed in several cases. According to the report, dues amounting to Rs 8.64 crore remained unpaid to 1,741 farmers as of April 2023.
The audit also flagged financial irregularities in JSFCL. It noted that the corporation submitted different financial statements for the same year to different authorities, raising concerns over financial reporting practices. It also pointed to pending recoveries from millers and irregularities in institutional processes such as board meetings and account maintenance.
The CAG report further indicated issues in other sectors, including avoidable expenditure and delays in project implementation.
According to the audit findings, the issues observed across PSUs point to gaps in planning, coordination and oversight in the implementation of public sector projects in the state.
You may like
-
Soren Marks Sarhul in Ranchi, Highlights Nature and Tribal Traditions
-
Chamber Raises Concerns Over Online Transport Processes in Jharkhand
-
Jharkhand Police Receive 1,485 Vehicles as 12 New Police Stations Announced
-
Jharkhand Budget 2026-27: Stability Over Spectacle, Delivery the Real Test
-
Ranchi Smart City Gets Land Mutation Clearance After 10 Years
-
HEC Revival Key to Jharkhand’s Industrial Comeback
Saffron robes may mark renunciation, but they do not define it: Swami Niranjanananda
Traffic challans dominate Ranchi Lok Adalat
Modi’s 76th birthday: month-long celebrations planned
Sudesh Mahto seeks ST status for Kudmi from Amit Shah
Rural economy key to inclusive growth, says Dipika
Ganga crosses four-year high in Sahibganj at 28.72 metres
JMM seeks probe into donations to unrecognised parties
BJP announces protests across Jharkhand over student cases
Jharkhand minister Sudivya Kumar Sonu dies in Giridih
BJP announces protests across Jharkhand over student cases
Jharkhand power bill to rise from April 1 as JSERC hikes electricity tariff
India International Mega Trade Fair 2026 in Ranchi
Palash: How Jharkhand’s Women’s Collective Became a Global Case Study
Ranchi to Get Jharkhand’s Largest Mall with Integrated ISBT
Bokaro Thermal Power Plant Shut Down, DVC Faces Heavy Costs
Toxic Profits: The Hidden Economy Behind India’s Polluted Rivers
Rivers on Life Support: The Poisoned Veins of Eastern India
BMW Industries to Invest Rs 803 Crore in Steel Plant at Bokaro, Jharkhand
Jharkhand Tribal Cinema: From Culture to Commerce
Jharkhand’s First Flying Institute Takes Off After 17-Year Wait
From Welfare to Enterprise: How Rs 2,500 a Month Is Helping Women Build Businesses in Koderma
Jharkhand’s Solar Policy: Decentralised Energy in Practice
JMM Exits Mahagathbandhan, Will Not Contest Bihar Assembly Polls
Birsa Munda’s Legacy Inspires Tribal Enterprise Push